Headline result: A comprehensive electrical assessment delivered a bankable roadmap and budget to install chargers at council depots.

At a Glance

Organisation: Regional council

Fleet: ~80 fleet assets

Scope: Depot charging planning

Regional council depot charging roadmap and load management

The Situation

The regional council wanted to understand where, how and how much it would cost to charge potential electric vehicles across its depots.

The Constraint

Grid capacity and connection requirements were major cost and lead-time considerations. Early electrical assessment was needed to shape the charging plan and budget.

What We Did

We assessed real fleet energy use, vehicle dwell times and site electrical capacity. We then planned the charging mix and load management before assessing potential infrastructure upgrades.

What We Found

Overnight AC charging could cover most fleet use, with DC charging supporting quick turnarounds. The mix depended on each depot’s operating requirements.

Specifying load management first identified opportunities to defer electrical upgrade works, subject to site capacity and network requirements.

What We Recommended

Size charging from real energy use, specify load management before pricing upgrades, and start grid connection applications early. Use the electrical assessment and staged roadmap to support a practical investment budget.